The Wilds Ninth and 11th Additions and Sanitary Lift Station - District No. 1305

About this Project

Infrastructure for The Wilds Ninth and 11th Additions and sanitary lift station.

Project Schedule

  • Begin Date: August 2017
  • End Date: July 2019
  • Project Complete: 
    • Ninth Addition: 95%
    • 11th Addition: 5%

Project Costs

  • Estimated cost: $6.7 million

Project Location - Ninth Addition

The Wilds Ninth Addition

Project Location - 11th Addition

District No. 1321 Special Assessment District Map

Completed Work

  • Ninth Addition
    • Pond
    • Utilities
    • Sanitary sewer lift station
    • Street lights
    • Sidewalk
    • Mailboxes
    • Park area storm sewer

Current Work

  • Ninth Addition
    • Final details
  • 11th Addition
    • Sanitary sewer
    • Sanitary main

Upcoming Work

  • 11th Addition
    • Road preparation at north
    • Install water main and storm sewer at south