Drainage Study Updates - Drains 21 and 45

Project Information

  • Estimated Project Costs: $39,480
  • Project Begin Date: April 2018
  • Project End Date: December 2018
  • Project Completion: 20%

Completed Work

  • Storm sewer plan set identification
  • Manhole survey identification
  • Data gap identification
  • West Fargo land use plan

Current Work

  • Topographical data collection and review at problem drainage areas
  • Input new topographical and manhole data

Future Work

  • Modeling of drains