Eagle Run Plaza Sixth Addition

Eagle Run Plaza Sixth Addition

About this Project

The purpose of the improvements is to provide new City infrastructure to service the Eagle Run Plaza 6th Addition development as petitioned by the developers. The improvements will service the new lots platted and will promote social and economic development in the proposed project area. The proposed infrastructure will allow development of the property, which is planned to be a mixed-use development providing a social-hub for the southern portions of West Fargo and the entire region. This project will help promote positive economic development along the Sheyenne Street corridor.

Sewer, Water, Storm and Street Improvement District No. 1314 will involve the construction of improvements consisting of sanitary sewer, water main, storm sewer, curb and gutter street pavement, driveways, street lights, sidewalks, on-street parking additions, signing, striping and other miscellaneous installations.

Project Schedule

  • Estimated Start Date: April 2018
  • Estimated End Date: October 2018
  • Percent Complete: 55%

Public Impact 

  • Some work temporarily on hold due to Sheyenne Street pedestrian underpass construction

Completed Work

  • Sanitary sewer and water system
  • Storm sewer
  • Street signs
  • Utility relocation
  • Man holes raised

Current Work

  • Concrete paving

Upcoming Work

  • Paving