Gateway West Addition (Site, Storm Sewer and Lift Station Improvements) -District No. 4065 and 1306

About this Project

The purpose of the proposed project is to install storm sewer, storm water ponds, and storm sewer lift station to service the Gateway West Addition. The need for the proposed project is warranted by the development of the Gateway West site and the request by the property owner to install the improvements. 

Storm Improvement District No. 4065 will involve the construction of improvements consisting of storm sewer, storm water retention pond, storm sewer lift station, and other miscellaneous installations

Project Schedule

  • Estimated Start Date: May 2018
  • Estimated End Date: October 2018
  • Percent Complete: 82.5%
    • Storm sewer and lift station: 85%
    • Site improvements: 80%

Completed Work

  • Sanitary sewer
  • Pond excavation
  • Storm sewer
  • Forcemain to Sheyenne Street
  • Transformer pad
  • Driveway

Current Work

  • Water main
  • Lift station
  • Seeding
  • Transformer pad
  • Conduit prep
  • Storm sewer on north half of site
  • Sanitary sewer televising

Upcoming Work

  • Backfill and seed driveway area