Sheyenne Street Segment 2 - Beaton Dr. to 32nd Ave

Sheyenne Street Segment 2 Finished Section Rendering

About this Project

Reconstruction of Sheyenne Street from Beaton Drive to 32nd Avenue to increase roadway capacity from one lane in each direction to three lanes in each direction. Includes installation of traffic signals at major intersections. Project coincides with I-94 interchange reconfiguration project.

Estimated Construction Cost

  • $24 million (partially funded by ND DOT)

Estimated Special Assessments

Project Schedule

  • Estimated Start Date: June 2018
  • Estimated End Date: October 2018

Road Closures

  • Sheyenne Street from 26th Avenue W. to 32nd Avenue W. estimated to reopen Oct. 13.
  • 26th Avenue W. closed at Sheyenne Street for reconstruction beginning Oct. 13.

SheyenneDetour_Phase 3

  • East- and westbound lanes adjacent to the medians on 32nd Avenue east and west of Sheyenne Street closed
  • Congestion and delays likely during peak traffic

Completed Work

  • Lift station sheeting
  • Temporary pipe crossings

Current Work

  • Sanitary sewer force main at diversion channel
  • Water main relocations
  • 29th Avenue W. pavement removals
  • Phase 2 scheduled to begin Aug. 15 with road closure from 26th Avenue W. to 32nd Avenue W.

Upcoming Work

  • Pavement removals from south of 26th Avenue W. to north of 32nd Avenue W.