Highland Meadows First and Second Additions - District No. 1295

About this Project

Infrastructure for Highland Meadows First and Second Additions development.

Project Schedule

  • Begin Date: August 2017
  • End Date: June 2018
  • Project complete: 99%

Completed Work

  • Underground utilities
  • Fabric and gravel
  • Curb and gutter
  • Asphalt paving
  • Path along 21st Avenue
  • Earthwork
  • Sidewalks
  • Seeding
  • Striping
  • Signs

Current Work

  • Diversion rear lot filling

Upcoming Work

  • Rear lot filling and stabilization
  • Culvert abandonment through levee
  • Waiting on 408 USACE permit